Decision
Matter of: TyeCom, Inc.
File: B-287321.3; B-287321.4
Date: April 29, 2002
Howard
Stanislawski, Esq., and Richard L. Larach, Esq., Sidley Austin Brown &
Wood, for the protester.
Moses
Harvin, for American Services Technology, Inc., an intervenor.
Joseph
A. Lenhard, Esq., and Timothy Fischer, Esq., Department of Energy, for the
agency.
Paul
I. Lieberman, Esq., and Michael R. Golden, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.

DIGEST
Protest against proposal reevaluation is denied where the reevaluation was performed by the agency in response to, and consistent with, corrective action suggested during alternate dispute resolution conducted in conjunction with a predecessor protest of the same procurement to the General Accounting Office, and the protester has not provided any persuasive evidence that the reevaluation was improper or unreasonable.

DECISION
TyeCom, Inc. protests the award of a contract to American Services Technology, Inc. (ASTI), under request for proposals (RFP) No. DE-RP09-00SR22183, issued by the Department of Energy (DOE) as an 8(a) small disadvantaged business (SDB) set-aside for administrative facility support services at DOE's Savannah River Operations Office. TyeCom contends that the agency's most recent technical and cost evaluation is “fatally flawed.” Protest at 1.
We deny the protest.
BACKGROUND
This procurement has had a protracted history, commencing
with DOE's issuance of the solicitation on March 18, 2000. On February 15, 2001, the agency initially
selected [deleted] proposal for award from amongst a final competitive range
consisting of three proposals, the others of which were the TyeCom and ASTI
proposals. TyeCom protested the award
determination to our Office on February 26, whereupon the agency
determined to reopen discussions and, on March 6, TyeCom withdrew this
protest.[1] After conducting additional discussions and
providing the offerors an opportunity to submit final proposal revisions (FPR),
the DOE source evaluation panel (SEP) evaluated TyeCom's proposal as
“acceptable” with a proposed cost-plus-fee of $8,003,798. ASTI's proposal was evaluated as
“exceptional” with a proposed cost-plus-fee of $8,921,239. Agency Report, B-287321.2, Aug. 10, 2001
(AR.2), Tab 4, Source Selection Decision, at 1-2. The two offerors had proposed virtually the identical existing
workforce, with the exception of three managers. The SSO reasoned that since TyeCom's proposal had been evaluated
as “acceptable” by the SEP, “from a technical standpoint, TyeCom should be
successful in performance,” and also believed that “[since] TyeCom has accepted
indirect rate ceiling rates, which protect the Government against increased
indirect costs (an eventuality I consider likely), cost risk is reduced to an
acceptable level.” Id.
at 2. In these circumstances, the
SSO decided that “[i]n terms of the evaluation criteria of the RFP, Tyecom
would be in line to receive the award.”
Id.
However, the SSO questioned TyeCom's responsibility based
on other available information, including that TyeCom had done very little
business during the [deleted] years that it had been in the 8(a) program, had
been, [deleted], essentially dormant for the past [deleted], had no [deleted]
for the year [deleted], and had [deleted] current business and only [deleted]
employee, [deleted]. Id. at
2-3. As a result, the SSO requested the
Small Business Administration (SBA) to review TyeCom's responsibility under
SBA's certificate of competency (COC) procedures. SBA issued a COC for TyeCom on July 2, 2001, after which DOE
determined to make award to TyeCom. In
particular, the SSO determined that TyeCom's lower technically rated, lower
cost proposal was in line for award on the basis that: “the overall advantage
the 'Exceptional' rated proposal of ASTI represents over the 'Acceptable' rated
proposal of Tyecom is one of degree. . . . [T]he incremental increase in
overall performance potential represented by the ASTI offer does not warrant
the increased cost of $917,441.” AR.2,
Tab 8, Source Selection Decision Addendum, July 17, 2001, at 4. On July 27, after receiving a debriefing,
ASTI protested this award determination to our Office.
Alternative Dispute Resolution Disposition of ASTI's
Protest
As a result of ASTI's protest, our Office conducted an
“outcome prediction” alternative dispute resolution (ADR) conference with the
parties.[2] During this conference, the GAO attorney
handling the protest explained to the parties that ASTI's protest was likely to
be sustained because the agency had awarded to TyeCom, which had submitted a
substantially lower-rated technical proposal, on the basis of TyeCom's low
proposed cost under a cost-reimbursement contract, without performing any
meaningful cost realism analysis on TyeCom's proposed costs, which the record
established were subject to serious question.
As a result of the ADR conference, the agency determined to take
corrective action in the form of conducting probable cost analysis of all
proposals and making a new award determination based on consideration of the
resulting cost and technical evaluations, along with a documented
cost/technical tradeoff, if appropriate.
Thereupon, on September 4, our Office dismissed ASTI's protest as
academic.
ADR Rationale
During the ADR conference, the GAO attorney pointed out
that the solicitation provided that technical was more important than cost,
which was being proposed on a cost-reimbursement-plus-fee basis. The solicitation further provided that the
agency would evaluate offerors' cost data to assess the accuracy and
reasonableness of the proposed cost and the probable cost to the
government. RFP § M.3(2). ASTI's proposal had received an overall
technical rating of “exceptional” while TyeCom's overall technical rating was
“acceptable”; TyeCom's proposed cost (including fee) was $8,003,798, while
ASTI's proposed cost was $8,921,239.
The offerors were proposing substantially the same labor force, and the
most significant cause for the cost difference was that TyeCom had applied a
flat 2.5 percent per year direct wage escalation rate over the life of the
contract, including options, while ASTI had applied a significantly higher wage
escalation rate which substantially reflected the rates contained in an
independent survey conducted by Data Resource Inc. (DRI) of labor escalation
rates for the industry. The Defense
Contract Audit Agency (DCAA), which reviewed the proposed costs for DOE, had
used DRI data as a measure of likely direct labor cost escalation, and during
discussions DOE had asked TyeCom about its flat, low proposed direct labor
escalation rate, requesting supporting documentation. Agency Report, B-287321.3, B-287321.4, Mar. 8, 2002 (AR.3),
Tab 12, TyeCom Discussion Questions, encl. 1, at 1. In response, TyeCom acknowledged that its
proposed escalation rate was below the DRI estimates used by DCAA; noted that
it had used a “conservative” 2.5 escalation rate “in the interest of being
price competitive”; stated that it desired to “retain the current work force in
place,” and had “proposed to pay current prevailing wages, an excellent fringe
benefits package and will offer competitive annual adjustments”; and indicated
its willingness to discuss a higher rate during contract negotiations. AR.3, Tab 14, TyeCom Discussion Response,
Aug. 28, 2000, at 5-6.
The agency eventually accepted TyeCom's flat 2.5 percent
escalation rate, without making a probable cost adjustment, despite the fact
that nothing in the record provided any basis to conclude that TyeCom would be
able to achieve this low wage escalation rate, beyond the fact that its initial
wages exceeded the Service Contract Act wage determination rates for the local
area. During the ADR conference, TyeCom
was provided an opportunity to point to anything in the record which supported
the artificially low escalation rate.
TyeCom's only response was that the proposals should be individually
evaluated and that TyeCom's low escalation rate was supported by the fact that
its initial wage rates exceeded the wage determination rates. However, this was also true, and, indeed, to
a greater extent for ASTI, which proposed the identical workforce at initial
wage rates which exceeded the wage determination rates, in some cases by more
than TyeCom; thus, TyeCom's initial rates did not provide a reasonable basis to
distinguish between the respective proposed direct wage escalation rates.
Nonetheless, DOE had not made any adjustments to TyeCom's
proposed cost, noting only that “[i]n as much as TyeCom has accepted indirect
rate ceiling rates, which protect the Government against increased indirect
costs (an eventuality I consider likely), cost risk is reduced to an acceptable
level.” AR.2, Tab 4, Source Selection
Decision, at 2. However, the indirect
rate ceilings are completely unrelated to the direct wage rates and thus cannot
reduce the government's risk with respect to the direct wage escalation
rate. In addition, the indirect rate
ceiling rates that TyeCom had proposed to accept were below the indirect
ceiling rates it had actually proposed in its cost proposal. That is, TyeCom could escalate its indirect
rates by amounts that would result in a cost increase that DOE conceded was in
excess of $200,000 before the ceilings were reached. Accordingly, the ceilings provided limited protection even with
respect to the indirect rates.
The GAO attorney noted during the ADR session that DOE had
improperly accepted TyeCom's apparently unrealistic proposed cost, without
performing an adequate cost realism analysis, and without making the required
probable cost adjustment. Accordingly,
the GAO attorney suggested that, since TyeCom's low cost had been
determinative, and the record showed that there was no basis to conclude that
this cost was realistic, the agency reevaluate proposed cost and make a new
award determination taking into consideration this reevaluation.
Reevaluation and New Award Determination
DOE subsequently decided to take this corrective action,
and in so notifying TyeCom, DOE advised that “[w]ith respect to labor
escalation rates, DOE intends to apply the appropriate Data Resource, Inc.
(DRI) labor escalation rates as the realistic measure of labor escalation to
each of the offerors' cost proposals.”
Protester's Comments, Mar. 18, 2002, attach. 1, SSO Letter to TyeCom,
Aug. 30, 2001. TyeCom, after having
fully participated in the ADR conference, and having received this specific
explanation of the specific method of cost reevaluation that the agency would
be implementing, did not protest either the agency's decision to conduct the
reevaluation, or the specified methodology for conducting the reevaluation.
As a result of the agency's revised cost evaluation, in
large measure because of the imposition of DRI wage escalation rates to both
proposals, TyeCom's final evaluated cost-plus-negotiated-fee was increased to
$8,889,202, and ASTI's evaluated cost was increased to $9,154,834. TyeCom's “acceptable” technical proposal
evaluation remained unchanged, as did ASTI's “exceptional” evaluation. Based on the results of this reevaluation,
the agency determined that the relatively small, $265,632, total cost advantage
(less than 3 percent of the cost total) associated with TyeCom's proposal was
outweighed by ASTI's substantial technical superiority under the most important
technical areas. In particular, the SSO
noted that there was a major technical difference in the strengths between the
offerors under the three most heavily weighted technical criteria and
subcriteria, under each of which ASTI's proposal was substantially higher
rated. AR.3, Tab 33, Source Selection
Decision, at 6-7. Accordingly, DOE
awarded ASTI the contract on January 10, 2002.
After receiving a debriefing from the agency, TyeCom filed this protest
with our Office on January 18, 2002, and later filed a supplemental protest
after receiving documents from the agency.
While TyeCom styles its protest as an objection to a wide
array of technical and cost evaluation, the real core of the protest is
TyeCom's objection to the agency's implementation of the corrective action
suggested during the ADR conducted in conjunction with the predecessor ASTI
protest. In our view, TyeCom has not
provided any persuasive evidence that the reevaluation and award are unreasonable
or improper, and the protest is entirely without merit.
PROBABLE COST EVALUATION
During ADR, the GAO attorney advised the agency that it
appeared to have failed to perform an appropriate and required cost evaluation,
and suggested that in the circumstances presented here, a normative application
of the DRI wage escalation percentages would be a reasonable step, at least as
a starting point. Because a GAO
attorney will inform the parties through outcome prediction ADR that a protest
is likely to be sustained only if he or she has a high degree of confidence
regarding the outcome, the willingness to do so is a sufficiently clear
indication that the protest is meritorious such that, absent persuasive
evidence to the contrary, such a prediction satisfies the requirement that we
conclude that a protest was “clearly meritorious” for purposes of recommending
reimbursement of protest costs. National
Opinion Research Center--Costs, B-289044.3, Mar. 6, 2002, 2002 CPD ¶
55, at 3. Similarly, an agency may
reasonably rely on such a prediction in implementing corrective action.
Here, DOE implemented corrective action that was precisely
consistent with GAO's ADR analysis, including the specific nature of the
suggested corrective action, after notifying TyeCom of its specific proposed
evaluation methodology. The cost
realism analysis and the resulting upward adjustments applied by DOE were
reasonable and consistent with both applicable regulatory guidance under
Federal Acquisition Regulation (FAR) § 15.404-1(d)(2), and with the
GAO attorney's suggestion during ADR.
TyeCom's protest does not provide any basis to question the agency's
action since TyeCom has merely recapitulated essentially the same argument it
presented during ADR, and has not provided any persuasive evidence that the
reevaluation was unreasonable.
Similarly, the new cost/technical tradeoff determination resulting in
selection of ASTI's proposal is reasonably based on the corrected cost
evaluations, and TyeCom has not provided any meaningful basis to question the
propriety of the determination.
TECHNICAL EVALUATION
TyeCom has also raised a broad array of objections
regarding various aspects of the agency's evaluation of its own and of ASTI's
technical proposals, which is unchanged from the initial evaluation, all of
which we have considered and find without merit. We will limit our discussion in this decision to a representative
example of these arguments.
Experience of TyeCom's President
In evaluating TyeCom's proposal as neutral for past
performance, and “acceptable” overall under the most important technical
criterion of Experience of Organization--Past Performance, the agency concluded
that TyeCom did not have demonstrated past performance related to the statement
of work. TyeCom asserts that it was
entitled to an exceptional rating under this evaluation factor based on the
past performance of its company president, and that DOE improperly failed to
credit this experience. TyeCom cites
FAR 15.305(a)(2)(iii) as requiring that “the evaluation take into account past
performance information regarding predecessor companies, key personnel who have
relevant experience, or subcontractors that will perform major or critical
aspects of the requirement when such information is relevant to the instant
acquisition.” Protest at 6. While, in fact, the FAR language cited by
the protester is precatory rather than mandatory, the simple and undisputed
answer is that for purposes of evaluation as key persons under section L-14 of
the RFP, the solicitation designated only the program manager and assistant
program manager. AR.3 at 6. TyeCom's company president was not proposed
to fill either position and therefore does not fall within the purview of the
key person requirement.
The agency also correctly points out that while, in
appropriate circumstances, an agency properly may consider the experience of
supervisory personnel in evaluating the experience of a new business, there is
no legal requirement for an agency to attribute employee experience to the
contractor as an entity. Hard
Bodies, Inc., B-279543, June 23, 1998, 98-1 CPD ¶ 172 at
4. Accordingly, the agency was under no
obligation to credit TyeCom as a corporate entity with the individual
experience or past performance of the company's president; TyeCom's protest
allegation is misplaced as to both fact and law.
COST EVALUATION VERSUS COC
Finally, TyeCom asserts that because the agency's cost
reevaluation included an adjustment of TyeCom's proposed indirect rates, it
constituted a “de facto nonresponsibility determination,” thus,
the agency “usurp[ed] SBA's legal authority to make responsibility
determinations for small businesses.”
Protest at 10. This argument
patently misconstrues the nature and effect of both the COC determination and
the probable cost evaluation. Under FAR
15.305(a)(1), when contracting on a cost-reimbursement basis, an agency is
required to perform a cost realism analysis to determine what the government
should realistically expect to pay for the proposed effort when
contracting. SBA's issuance of a COC
constitutes an affirmative determination of responsibility with respect to
responsibility elements such as capability, competency, credit, integrity,
perseverance, tenacity and limitations on subcontracting. FAR 19.601.
An affirmative determination with regard to these kinds of
responsibility considerations is separate from and unrelated to a probable cost
adjustment, as required by the FAR and specifically called for here under the
RFP, in conjunction with performing a cost realism analysis. Accordingly, this allegation provides no
basis to question the agency's probable cost adjustment or reevaluation.
The protest is denied.
Anthony H. Gamboa
General Counsel
[1] Performance
under each of the contract award decisions from February 15, 2001, until the
present has been stayed by DOE because of the protests. As a result, performance of the work at
issue has continued by the incumbent, Madison Research Group (MRG), a non-SDB,
with Systems Support Alternatives, Inc. (SSA), another non-SDB, performing as
MRG's subcontractor for certain of the operations. In the current SDB set-aside competition, TyeCom has proposed SSA
as its subcontractor, and ASTI has proposed MRG as its subcontractor.
[2] In outcome
prediction ADR, the GAO attorney handling a protest convenes the parties, at
their request or at GAO's initiative, and informs the parties what the GAO
attorney believes the likely outcome will be, and the reasons for that belief,
including the form of corrective action that our Office would likely recommend
where the protest is likely to be sustained.
A GAO attorney will engage in this form of ADR only if she or he has a
high degree of confidence regarding the outcome. Where the party predicted to lose the protest takes action
obviating the need for a written decision (either the agency taking corrective
action or the protester withdrawing the protest), our Office closes the
case.