| Name | Agency | Telephone |
|---|---|---|
| Mathew Blum | OFPP/OMB | 202-395-4953 |
| Gena Cadieux | Department of Energy | 202-586-6902 |
| John Cornell | GSA (OGC) | 02-501-1156 |
| LTC Doug DeMoss | Army OGC | 703-697-5120 |
| Patrick Drury | Army CECOM Acquisition Center | 703-325-3359 |
| Thomas Duffy | Army, Contract Appeals Division | 703-696-2825 |
| Paul Fisher | NAVAIR | 703-604-2411x3116 |
| Michael Gerich | OFPP/OMB | 202-395-6811 |
| Bob Gorman | DOD/OGC | 703-697-5073 |
| Elizabeth Grant | DLA | 703-767-6078 |
| LTC Richard Hatch | Army Litigation | 703-696-1635 |
| Craig Hodge | Army Materiel Command | 703-617-8940 |
| Andrei Kushnir | SPAWAR (Navy) | 703-602-8459 |
| Mark Langstein | Commerce OGC | 202-482-1122 |
| Clarence D. Long, III | Air Force (OGC) | 703-697-3900 |
| Kirk Manhardt | DOJ, Commercial Litigation | 202-514-4325 |
| LTC Larry Passar | DOD/AR | 703-614-3882 |
| Steve Schooner | OFPP | 202-395-3501 |
| Jared Silberman | AGGROLA NISMC | 703-602-6279 |
| Sumara Thompson-King | NASA/GC | 202-358-2075 |
| Jerry Walz | Commerce OGC | 202-482-1122 |
A. The Court Should Review A Limited Administrative Record.;
B. Discovery Should Be Limited.
C. Where There Has Been a Prior GAO Protest, the
Court Should Consider The Agency Report As
Part of The Administrative Record.
D. In Limited Circumstances, Particularly Absent A
Prior GAO Protest, Agency Supplementation of
the Administrative Record May Prove
Appropriate .
E. Limited, Appropriate Supplementation of The
Administrative Record Should Not Lead to
Unfettered Discovery.
F. The Court Should Provide Guidance Regarding
Protective Orders.
V. The Court Should Resolve Disappointed Offeror Cases
Promptly And Efficiently.
A. The Court Should Resolve These Cases Expeditiously.
B. Prompt Resolution Should Be Tempered With
The Need For Understanding and Preparation.
C. The Court Should Apply The Appropriate Legal
Standard For Issuing TROs and PIs; "Automatic
Stays" Are Inappropriate.
D. Suits Must Be Promptly Filed; The Doctrine of
Laches May Assist The Court.
E. The Court Should Require The Posting of Security.
VI. The New Statute Limits The Available Monetary Relief.
Attachment 1: Suggested Issues "Not For Consideration"
I. Introduction.
In light of the recent amendments to 28 U.S.C. § 1491,
See footnote 1 Chief Judge Loren Smith
established the Bid Protest Group of the United States Court of Federal Claims Advisory
Council. The group includes Judges of the Court and members of the private and public
bars. On March 4, 1997, the group held its first meeting. The group intends to gather and
review information on disappointed offeror litigation practice and procedure and submit a
report to the Advisory Council.
At the request of the Bid Protest Group, the Inter-Agency Working Group on
Federal Court Disappointed Offeror Litigation submits this White Paper. The White
Paper contains recommendations and analysis on a broad range of issues related to
disappointed offeror litigation before the Court. The White Paper reflects the general
consensus of a diverse group of experienced government attorneys rather than the specific
views of any given agency.
See footnote 2
We intend this information to assist the various subcommittees of the Bid Protest
Group in completing their work. We also encourage the liberal copying and use of any
information contained in this White Paper, without need for attribution, in any related educational or instructional materials.
II. There Is A Need For Court Guidance.
Initially, we believe the Court generally should process disappointed offeror
litigation in a manner similar to the traditional administrative protest forum, the General
Accounting Office (GAO). GAO has extensive experience with protests and has
established the benchmark against which any judicial forum inevitably will be measured.
In addition, both Government and civilian practitioners are familiar with the
administrative protest practice, and procedures are in place to respond to such protests
without undue difficulty.
One of the most attractive features of GAO practice is the clear legal procedural
guidance promulgated by GAO. Extensive rules and helpful GAO guidelines are readily
available to the public, in both the Code of Federal Regulations and through a GAO
publication. We believe that all parties will benefit if the Court is able to communicate
similar information, whether through rules or guidance, to the public. Publication of this
information could reduce the number of improperly filed suits, the amount of inefficient
jurisdictional motions practice, the resources devoted to procedural disputes, and the
cumulative disruption to the Federal procurement system.
We further encourage the Court, to the extent possible, to closely track GAO's
published bid protest rules and precedent. Maintaining consistent administrative and
judicial precedent is essential to the orderly conduct of the Government's business. The
substantial body of existing bid protest decisional precedent affects millions of
procurement actions taken each year. Disparity in jurisdictional matters can potentially
disrupt the conduct of procurements in ways that are not readily apparent. Commerce functions most efficiently when rules are clear and are applied in a consistent manner.
People engage in market transactions based upon certain expectations regarding the
process. To the extent that the Court diverges significantly from established precedent,
uncertainty will result, at the expense of the orderly conduct of the Government's
business.
III. The Court Should Clearly Articulate The Standard And
The Scope of Review.
A. The Court's Standard Should Require Demonstration of
Prejudicial Error With A Clear and Convincing Showing
That The Plaintiff Had a Reasonable Likelihood of
Receiving Award But For the Alleged Agency Error.
The new statute prescribes that the United States Court of Federal Claims (the
Court) and the Federal district courts are to review the agency's procurement decision
pursuant to the Administrative Procedure Act standard set forth in 5 U.S.C. § 706. Thus, the new statute adopts the established standard of judicial review of administrative agency
actions. Consequently, the Court should only set aside an agency procurement action
when it is necessary to correct a clear and prejudicial abuse of discretion or a clear and
prejudicial failure on the part of the agency to comply with procurement laws and
regulations. Absent such an abuse or failure to comply with the law, the Court should
defer to the judgment of the agency official who made the challenged decision. In
resolving these matters, the Court should bear in mind that the agency decision need not
be the only reasonable one or the decision the Court would have reached if it had been
responsible for the action.
Deference to the agency is the norm in judicial review of many types of agency
actions. In applying this standard to procurement decisions, such deference is particularly
appropriate because the agency is essentially making a business decision directed toward
fulfilling an agency requirement. Disappointed offeror litigation does not arise from the
adjudication of an entitlement or right.
To constitute an abuse of discretion, the agency decision must be determined to
have been arbitrary and capricious, that is, "wholly without reason." The Court applied
this standard in its February 25, 1997 decision on the merits in Cubic Applications, Inc. v.
United States, No. 97-29C, 1997 WL 76781 (Fed. Cl., Feb. 25, 1997). The Court also
used this standard in pre-award cases in exercising its jurisdiction before the new statute
expanded the Court's jurisdiction to hear post-award protests. See Compubahn, Inc. v.
United States, 33 Fed. Cl. 677 (1995) (considering a protest of non-selection of claimant's
proposal for an award as an alleged breach of implied contract to fairly consider the
proposal). If an agency decision is not arbitrary and capricious, it should not be reversed,
even if the Court would have reached a different conclusion. Cf. TRW Inc. v. Widnall, 98
F.3d 1325, 1327 (Fed. Cir. 1996) (reversing GSBCA decision wherein the Board
substituted its judgment for that of the agency). See also Widnall v. B3H Corp., 75 F.3d
1577 (Fed. Cir. 1996) (same result; the Board should have deferred to the reasonable
decision of the Source Selection Authority).
To establish either a reversible abuse of discretion or a reversible violation of
procurement laws or regulations, a plaintiff must show not simply a significant error in
the procurement process but also that the error was prejudicial. The plaintiff must convincingly demonstrate that, but for the alleged error, there was a "substantial chance"
it would have received the award. See Statistica, Inc. v. Christopher, 102 F.3d 1577 (Fed.
Cir. 1996) (ruling that the "reasonable likelihood" standard articulated by the court in
Data Gen. Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed. Cir. 1996), was virtually
synonymous with the "substantial chance" standard).
The Court has often applied a "clear and convincing" burden of proof upon the
plaintiffs in actions of this sort. See, e.g., Court of Federal Claims Gearing Up for New
Protest Authority, Questions Arise, 66 Fed. Cont. Rep. 449 (November 4, 1996). Such a rigorous standard should be met before setting aside an agency's procurement decision.
A lesser standard of proof could result in undue interference by disgruntled or
disappointed offerors with the efficient acquisition of government goods and services. Thus, for a plaintiff to sustain its burden of proving that it had a "substantial chance" (or a
reasonable likelihood) of receiving an award but for an error in the procurement process,
it must make this showing clearly and convincingly.
B. The Court Should Define The Scope of Protestable Matters.
The new statute now provides that the Court's disappointed offeror jurisdiction
extends to objections to solicitations, objections to awards and proposed awards of
contracts, and objections to alleged violations of statute or regulation in connection with a
procurement or a proposed procurement. 28 U.S.C. § 1491(b)(1). Although the wording
is not identical to the language that defines the GAO's jurisdiction, there is a high
correlation. (GAO's bid protest jurisdiction, under 31 U.S.C. § 3551, extends to objections to solicitations and objections to awards and proposed awards of contracts.
Under 31 U.S.C. § 3552, the objections raised by protesters must concern alleged
violations of a procurement statute or regulation.) Thus, it appears that, in amending 28
U.S.C. § 1491, Congress generally intended to permit the Court to consider similar issues
that are protestable at the GAO. Congress did not clearly express an intent to provide
offerors with the opportunity to litigate, before this Court, an expanded array of
procurement issues.
We encourage the Court to publish guidance or establish rules that clearly define
those matters subject to review under its new jurisdiction. GAO summarily dismisses
protests or specific protest allegations that are not properly before GAO for a number of
reasons. GAO includes, as part of its published Bid Protest Regulations, a list of "protest
issues not for consideration." 4 C.F.R. 21.5, 61 Fed. Reg. 39039 (July 26, 1996). This
list includes eight broad issues which GAO will not consider. We encourage the Court to
consider publishing similar guidance. Attachment 1 to this White Paper is a list of issues
which the Court might discourage litigants from raising under 28 U.S.C. § 1491(b).
We are mindful that, unlike the GAO, the Court has additional jurisdiction under
the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613, to review matters arising under
or related to a contract.
See footnote 3 Because the procedures and standards of review are necessarily
different for review of bid protest matters as opposed to CDA matters, we recommend
that the Court clearly identify in its rules which issues it will consider under each
jurisdictional grant.
IV. Consistent With The APA, The Court's Review Should Rely
Primarily Upon The Administrative Record.
A. The Court Should Review A Limited Administrative Record.
Discovery should be limited to what has generally been considered the "record," as
defined in bid protest practice before the GAO. Accordingly, we encourage the Court to
publish guidance for litigants that describes the anticipated scope of the administrative
record. Under this practice, documents considered to be part of the record, and thus
discoverable, would include, where appropriate:
* The solicitation with all amendments thereto;
* The rating plan or instructions to evaluators concerning how
proposals should be evaluated;
* The plaintiff's and awardee's initial proposals;
* Documents reflecting the agency's evaluation of the
plaintiff's and awardee's initial proposals;
* Correspondence between the agency and the plaintiff or
awardee;
* The agency's competitive range determination;
* A record of "discussions" with the plaintiff and awardee;
* The agency's request for submission of best and final offers (BAFOs);
* The plaintiff's and awardees BAFOs (not to include other offerors);
* Documents reflecting the agency's evaluation of the
plaintiff's and awardee's BAFOs, including technical and cost
or price evaluations;
* DCAA (or other agency audit organization) audits of
proposals where there are issues concerning the cost or price
evaluation;
* The government's cost estimate of the procurement;
* The source selection statement;
* The executed contract;
* Notice of award; and
* Prior agency-level protests, filed by the plaintiff, which
concern the same procurement, and any agency response to
such protests.
B. Discovery Should Be Limited.
To the extent that the new statute envisions record review, we encourage the Court
to limit permissible discovery. Discovery into matters outside of the administrative
record, as a general rule, is irrelevant and unnecessary.
In the Court's first published decision under its recently expanded jurisdiction, the
Court determined that discovery, while available, is subject to greater limitations than in a
de novo proceeding. Cubic, 1997 WL 76781, citing, Citizens to Preserve Overton Park v.
Volpe, 401 U.S. 402, 420 (1971). We agree with the Court's finding, as applied to the
facts in that case, that: "Although discovery may be appropriate as a necessary means to
understand the agency's action, it normally would not be likely to lead to relevant
evidence given the truncated nature of the court's review."
We appreciate the Court's decision in Cubic to disapprove four of the five requests
for dispositions. However, we encourage the Court to go further. Where the Court
believes that examination of the agency record alone is insufficient to determine whether
the agency properly awarded the contract, the Court could direct that the agency
supplement, to the extent possible, the existing record with additional documents that are
not ordinarily part of the record.
C. Where There Has Been a Prior GAO Protest, the Court
Should Consider The Agency Report As Part of The
Administrative Record.
When the Court reviews a bid protest matter that was subject to a prior GAO
protest, 31 U.S.C. § 3556 mandates that the Court consider -- as part of the agency record
subject to review -- the report that was submitted by the agency to GAO in accordance
with 31 U.S.C. § 3553(b)(2). That report includes all relevant documents, including a
post-decisional explanation by the contracting officer of the relevant facts in response to
the protester's allegations. 4 C.F.R. 21.3.
See footnote 4
We believe that documents included in the agency report to GAO should be
viewed as a part of the administrative record, rather than as a supplement to the record.
At this point, the Court is not simply reviewing an initial agency decision, but is
essentially reviewing the agency's ultimate action in response to the GAO
recommendation -- often in compliance with that recommendation, but not always.
Certainly, if compliance with the GAO's recommendation caused the agency to select a
different awardee from the one originally selected, and the Court action is being brought
by that originally proposed awardee to preclude award to another, the entire record of the
GAO proceedings must be considered to evaluate fairly the agency's action in response to
the GAO recommendation. Even if such a change in the agency's position did not occur,
its reaffirmation of its initial decision during and after the GAO proceedings should be
considered the decision that the Court is being called upon to review, and the full existing
record of its justification for its actions should be considered by the Court.
D. In Limited Circumstances, Particularly Absent A Prior GAO
Protest, Agency Supplementation of the Administrative
Record May Prove Appropriate.
We recognize, as did the Court in Cubic, supra, citing Camp v. Pitts, 411 U.S. 138
(1973), that judicial review of an administrative decision ordinarily is based upon the
administrative record in existence at the time of the decision. The Court considers the
material the agency developed and considered in making its decision, rather than a new
record made in the course of the litigation before the Court. We also recognize that "post
hoc" rationalizations of an agency's action may not be sufficient, standing alone, to show
that the agency's action was grounded in reason and otherwise proper. See Citizens to
Preserve Overton Park v. Volpe, 401 U.S. 402, 420 (1971).
Nevertheless, we urge the Court to recognize that there may be instances in which
the Court may require the agency to provide limited supplementation of the
administrative record that originally was assembled during the conduct of the
procurement. We believe that such supplementation of the record would be justifiable
under the standards articulated in Esch v. Yeutter, 876 F.2d 976 (D.C. Cir. 1989).
While the record of a procurement action ordinarily reflects the significant and key
considerations underlying the agency decision, it may be helpful to the Court to allow
additional written explanation of whether, how, and why the agency handled the issue
that is now being subjected to a "post-decisional attack" or whether the agency considered
evidence not apparent on the face of the record. This written explanation may provide the
Court with a clearer understanding of what transpired during the procurement process.
This may be particularly necessary if the Court is the first forum in which the agency
action is being challenged.
In such instances, the appropriate remedy for the Court to obtain the required
information should be a remand to the contracting officer. When necessary, the Court
could direct the contracting officer to consider the issue or matter not addressed in the
administrative record.
See footnote 5 Remand, in these limited circumstances, may expedite a
resolution, especially where the decision being reviewed was not previously subject to an
administrative protest.
E. Limited, Appropriate Supplementation of The
Administrative Record Should Not Lead to Unfettered
Discovery.
There may be instances where it may be appropriate for the agency to supplement
the record, when it is deemed necessary for a clear understanding of what transpired
during the procurement process. Where supplementation of the administrative record is
required, it should not normally "open the door" to discovery, particularly cross-
examination of the decision-makers by depositions or in court testimony. To the extent
that discovery is allowed, it should not be permitted to exceed the scope of the area or
areas for which supplementation of the record was authorized by the Court. See, e.g.,
Cubic, supra.
See footnote 6
F. The Court Should Provide Guidance Regarding Protective
Orders.
In soliciting bids and proposals from private sources, the Government frequently
requires offerors to furnish proprietary information. Proposals routinely include an
offeror's prices, labor rates, overhead costs, proprietary processes and methodologies,
staffing plans, etc. This information is considered proprietary and offerors routinely insist
that the release of such information would injure their competitive capabilities.
Congress has recognized that proprietary information should be protected from
disclosure to the public or a company's competitors, and has enacted a number of statutes
which prohibit federal employees from disclosing such information. See, e.g., the Trade
Secrets Act, 18 U.S.C. § 1905, the procurement integrity provisions of the Office of
Federal Procurement Policy Act, 41 U.S.C. § 423,
See footnote 7 and the exemption from release of
proprietary information in the Freedom of Information Act, 5 U.S.C. § 552(b)(4).
See footnote 8
Unauthorized release of such information risks both criminal and civil penalties. The
statutes thus permit offerors to freely disclose proprietary information to the Government,
for its consideration in evaluating proposals, with a measure of assurance that an offeror's
proprietary information will not be disclosed to its competitors.
See footnote 9
In addition to proprietary information which is generated by an offeror, the
Government generates confidential commercial information such as source selection
information, which is not publicly releasable or disclosed to the competing offerors. Such
information is particularly sensitive during the procurement and evaluation process as it
includes the Government's "cook book" (or rating system) which is used in evaluating
proposals, the actual evaluation scores and narratives, etc.
See footnote 10
Obviously, this situation, in which the Government cannot disclose information,
conflicts with the general principles of public proceedings and the right of a party/litigant
to discover and present evidence to the fact finder. The common means by which these
apparently conflicting public policies has been resolved is through the use of protective
orders issued by a court or administrative body.
The orders permit counsel for disappointed offerors to discover and present in
evidence any proprietary or source selection information relevant to the allegations
pertinent to a protested procurement. As the release of such information would be
injurious to the competitive position of the offerors, such information cannot be revealed
or discussed by counsel with his or her client. Further, because of the sensitivity of such
information, the proceedings frequently must be closed, in whole or in part, to the public
and, more specifically, the litigant/clients (including the party bringing the action or an
interested party intervenor, such as an awardee) in order to prevent the release of
proprietary or source selection information. To the extent counsel cannot adequately
analyze financial or technical matters, the party can obtain an expert to review the
documents, if access is granted by the court or administrative body, to provide advice and
assistance to counsel.
The protective order thus functions like a tent. During the evaluation process, the
Government reviews (and generates) proprietary and source selection information within
the tent, but cannot disclose it, with few exceptions, to parties outside the tent. As a result
of the protective order, the court and all counsel who are authorized access to the
information, can enter the tent, and are free to review and analyze the information. The
proceedings essentially take place within the tent. Within that context, all the parties, to
include the decision-maker (whether a court or administrative body) can freely discuss the
protected information. The only inhibition is that the information cannot be disclosed to
parties outside the tent.
Protective orders and this process of protecting and restricting the release and use
of information are peculiar to post-award proceedings, precisely because the critical
information which is the subject of the proceeding involves proprietary or source
selection information. The fact that the award has been made, however, does not
ameliorate the need for continued protection of the information. The need for continued
protection derives from the remedies the court or administrative body may consider.
Protection of the information is particularly important if the court determines that the
Government violated a procurement law or regulation in such a manner as to prejudice
the plaintiff. Frequently, the remedy or order will direct the Government to re-evaluate
the proposals, or to conduct discussions and permit the submission of another round of
offers, etc. Thus, the inadvertent or other release of proprietary or source selection
information during a proceeding will irreparably affect the ability of the Government to
maintain the competitive process, as competing offerors will be privy to pricing or other
proprietary information of the other offerors, the Government's "cook book" for
evaluating proposals, etc.
Protective orders and their related processes have been de rigoreur for proceedings
before GAO. GAO permits disappointed offerors full access to and use of all pertinent
source selection and proprietary information in proceedings. The early issuance of
protective orders is more critical at the Court than it is at the GAO, as the Government
has up to 30 days to provide the parties and the GAO with its report. Given the nature of
the equitable relief sought before the Court, and the need to make even earlier production
of the administrative record, the immediate issuance of a protective order by the Court
would facilitate the litigation by permitting the parties to obtain documents much sooner
(particularly in those cases in which a protest was not previously filed with the GAO).
Various courts have recognized the place and role of protective orders and related
procedures. See, e.g., Fed. R. Civ. P. 26(c)(7). These procedures constitute an
appropriate balance of the divergent public policies of protecting information and the
right of a disappointed offeror to "have his day in court" by permitting his or her counsel
(and where appropriate, his or her experts), to discover and present all relevant facts in
proceedings before the Court. See, e.g., ITT Electro-Optical Prods. Div. of ITT Corp. v.
Electronic Tech. Corp., 161 F.R.D. 228 (D.C. Mass. 1995).
Therefore, we encourage the Court to establish standing procedures and to adopt a
model protective order, which can be tailored by the Court and the parties, as appropriate.
We urge the adoption of procedures used before the GAO as those procedures have been
accepted by the Government and the private bar, the parties are familiar with them, and
they are essentially incorporated in whole or in part in the proposed protective orders
submitted to the Court by the private bar.
See footnote 11
V. The Court Should Resolve Disappointed Offeror Cases
Promptly And Efficiently.
A. The Court Should Resolve These Cases Expeditiously.
The new statute mandates that the Court "give due regard to the need for
expeditious resolution of the action" in exercising its new jurisdiction. 28 U.S.C. §
1491(b)(3). In accordance with this requirement, we encourage the Court to adopt rules
to ensure that actions are processed as quickly as possible.
Executive agencies conducting procurements, as well as interested parties to those
procurements, benefit from a uniform standard with regard to processing time. Time and
resources could be apportioned more beneficially, by all parties, if it is known that a
decision will be received no later than a certain date. In general, we encourage the Court
to strive to meet or beat the GAO protest processing time.
For example, GAO is required to render a decision within 100 calendar days. 31
U.S.C. § 3554(a)(1). This rule also indicates that the GAO time limit was established to
facilitate the "expeditious resolution of protests." Similarly, the new statute mandates that
the Court "give due regard to the need for expeditious resolution of the action." Absent
extraordinary circumstances, the Court should be able to meet or exceed the speed with
which GAO disposes of protests.
B. Prompt Resolution Should Be Tempered With The Need For
Understanding and Preparation.
Although we encourage prompt resolution of these actions, we encourage the
Court to be mindful of the benefits associated with permitting the opportunity for
preparation prior to holding an initial hearing. Specifically, we recommend that the Court
allow a reasonable period of time before the initial conference on a temporary restraining
order (TRO) or preliminary injunction (PI), should such relief be requested. In post-
award procurement actions, the Government must assess the harm to the agency should
the TRO be granted. In making that determination, the Government frequently must
obtain an assessment from the contract awardee regarding what costs it has incurred and
what costs it will charge the Government should the TRO be granted. Furthermore, some complaints involve procurements in different areas of the United States and overseas. In
addition, counsel for the Government (from the Department of Justice) will be seeing the
complaint for the first time. The agency counsel and contracting officer(s) need some
time to read and discuss, with appropriate procurement officials, the complaint and the
potential harm to the Government. We recommend that the conference with the Court be
conducted no earlier than seventy-two hours after the complaint has been served on the
Department of Justice. If a complaint is served on a Friday, or the last business day of the
week, we recommend that the initial conference be conducted no sooner than 1:00 p.m.
on the third business day of the following week.
Further, we recommend that the Court adopt as one of its rules a requirement for
the plaintiff to furnish a copy of its complaint to the contracting officer by hand (or such
other means that will provide immediate notice of the filing). This rule would parallel a
similar rule at the GAO. GAO does not notify the contracting officer of the protest, nor
do we propose that this responsibility be imposed upon the Clerk of the Court.
A rule for notifying the contracting officer would not be onerous, as it would
impose the burden upon the plaintiff, who already knows the identity and location of the
contracting officer whose actions are usually the subject of the complaint. As post-award
proceedings are time-sensitive, providing a copy of the complaint to the contracting
officer will facilitate the compilation of the administrative record, particularly in
procurements which have not previously been protested to the GAO. Notice to the
contracting officer will trigger the agency's assembly and reproduction of the
administrative record and will ensure that documents which address the issues raised in
the complaint are included in the record. This rule would benefit all parties by speeding
the production of the administrative record and permitting the Court and the parties to
quickly address the merits of the complaint. Finally, notice to the contracting officer
would also lead to a more informed Government position at the initial conference called
to consider the need for TROs or PIs.
Similarly, in the spirit of judicial efficiency, and consistent with the Court's and
the Government's support for Alternative Dispute Resolution (ADR), we would support a
Court requirement for a mandatory meeting of counsel prior to the initial conference.
(Logically, the utility of such a meeting would depend upon a minimal, yet sufficient,
amount of time for the contracting officer, agency counsel, and the Department of Justice
to read, consider, and discuss the complaint.) This meeting could be accomplished by
telephone conference.
C. The Court Should Apply The Appropriate Legal Standard
For Issuing TROs and PIs; "Automatic Stays" Are
Inappropriate.
We believe that the issue of post award stays of performance is not an area where
agencies ought to routinely be asked to voluntarily halt contract performance, nor should
TROs or injunctions be routine. We encourage the Court, in a manner similar to the Federal district courts, to continue to place a heavy burden on any party that seeks
injunctive relief in bid protests.
In its "Court Approved Guidelines" dated December 11, 1996, the Court states that
the assigned judge will enter an order on the TRO "[i]f the Government does not agree to
defer action until the matter is resolved." We are concerned by, and would object to, any
implication that there is a presumption that the Government, as a matter of practice,
should defer action.
The implications of this statement likely grew out of the Court's experience with
the Government's greater willingness to defer action in preaward protests. We note,
however, that the manner in which stays should be conducted is different depending on
whether the protest concerns a preaward or post award matter. The administrative protest
practice is for preaward activity to be allowed up to the point of award. During that
period, agencies typically are more willing and able to agree not to make an award in the
face of a protest. Conversely, a post award protest often presents impediments to any
voluntary stay of performance by the Government.
Clearly, agencies consider deferral in all appropriate cases. After consideration,
in some cases, agencies may conclude that a stay in performance is in the Government's
interests. In many other cases, however, contract performance must commence. The Court should clarify that there is no presumption that the Government should defer action
simply because a plaintiff applies for injunctive relief.
D. Suits Must Be Promptly Filed; The Doctrine of Laches May
Assist The Court.
The new statute does not require that disappointed offeror suits be filed within any
particular time period. This lack of certainty, regarding when such an action may be
considered timely, could disrupt the procurement process, and appears to be at odds with
the current emphasis on attaining greater efficiencies in that process.
Generally, post award bid protests at the GAO must be filed within ten days after
specific events. 4 C.F.R. § 21.2. If the agency does not receive a protest within that time
frame, it can reasonably conclude that a timely protest is unlikely to be filed. This allows
the agency to make resource and personnel decisions without the fear that these decisions
will be disturbed by a subsequent bid protest. The absence of specific filing deadlines for
disappointed offeror suits filed with the Court is likely to frustrate the efficient utilization
of resources and personnel. Therefore, we encourage the Court to impose specific filing
deadlines, similar to those at the GAO, in order to eliminate this uncertainty. In the
alternative, we encourage the Court to at least presume that any suit filed beyond those
widely recognized administrative protest deadlines has been inexcusably delayed, with
material prejudice to the Government.
Such a decision is not unheard of in the courts. In Saco Defense Sys. Div. v.
Wienberger, 629 F. Supp. 385 (D. Me.), aff'd, 806 F.2d 308 (1st Cir. 1986), both the
district and circuit courts cited the GAO rules and found the plaintiff's delay in filing a suit alleging a defect in the solicitation precluded it from raising the issue following
contract award. The court's rationale in Saco was that "[i]f they [the protester] had
wanted to challenge the ten percent [evaluation] factor, they should have done it before
the close of bidding, at a time when its correction, if necessary, could be effected without
necessitating the undoing of all the spare parts cost evaluation performed by the
Defendants." 629 F. Supp. at 387-88. Similarly, in Airco, Inc. v. Energy Research &
Dev. Admin., 528 F.2d 1294 (7th Cir. 1975), the court found that the plaintiff had waived
its right to challenge the change in the specifications because it failed to raise the issue in
a timely fashion. Again, the Court applied the GAO rules for timely filing of the protest.
See also, Alliant Techsystems v. United States Dep't of the Navy , 837 F. Supp. 730, 737
(E.D. Va. 1993) ("It is well established that bidders who fail to make timely protests
regarding improper bid solicitations waive their ability to protest.").
Furthermore, the Court has recognized the utility of this pragmatic limitation. In
Aerolease Long Beach v. United States, 31 Fed. Cl. 342 (1994), aff'd, 39 F.3d 1198 (Fed.
Cir. 1994), the Court stated:
In short, the defendant asks this Court to apply the requirements of the
GAO bid protest regulations. See 4 C.F.R. § 21.2(a)(1) (1992) [quoted
regulation omitted.] While this Court declines to accept this regulation as
controlling in all cases, the defendant persuasively demonstrates the utility
of the GAO rule in the bid protest arena. See Logicon, Inc. v. United States,
22 Cl. Ct. 776, 789 (1991) (finding favor with the timeliness regulations of
the GAO for bid protests). If an offeror recognizes an ambiguity or other
problem in the solicitation, proper procedure dictates that the offeror
challenge the problem before submission of an offer. If the offeror declines
to challenge the problem, the reviewing tribunal may find that the offeror
waived its right to protest. . . . In circumstances such as these, this Court
finds the application of the GAO rule fitting, based not on adoption of the
regulation but on the wide discretion afforded the contracting officer to
conduct negotiations pursuant to the terms of the SFO.
31 Fed. Cl. at 358. Thus, although the Court declined to adopt the timeliness regulations
of the GAO, it recognized the utility of the rules and effectively implemented them.
Case-by-case acceptance of such rules, however, is neither orderly nor efficient.
Although Congress intended to expand the Court's jurisdiction, there is no reason
to believe that Congress intended to provide disappointed offerors with a means to evade
reasonable time limits within which a suit must be filed. The recent acquisition reform
statutory changes, from which these guidelines are extracted, give considerable weight to
the importance of Government acquisition by imposing tight, yet realistic, limits on the
time window within which a protest must be resolved. These statutory time frames, in
conjunction with implementing regulations, are effectively a statute of limitation on a
frustrated bidder's attempt to right an alleged wrong, which a court of equity ought to
honor in deciding whether an equitable proceeding, seeking injunctive relief will lie.
The same time limitations applied to administrative protests should also apply
where an action is initially filed in the Court. Similarly, where a plaintiff has previously
attempted to seek relief, through the contracting officer, the agency, or the GAO, then the
applicable time frames should be those applied by regulation to determine the timeliness
of a protest filed with GAO after an agency-level protest was previously filed. GAO's
bid protest regulations, 4 C.F.R. § 21.2(a)(3), allow protests to be filed within ten days of
an agency's initial adverse action on an agency protest.
Sound reasons justify applying these limits. During the early stages of a
procurement, the time lost by the Government in defending a court suit can often be made
up by accelerating later stages of the acquisition process. However, after initial proposal
submission, as competition proceeds to the latter stages (and award), the Government's
ability to make up for time lost in defending litigation becomes increasingly
compromised. Thus, it is incumbent upon protesters or plaintiffs to surface any
complaints soon after they become apparent, rather than waiting until the procurement
has gone further down the track and the prejudice to the Government, and to other
competitors, becomes manifest.
Prejudice resulting from delay in filing may take many forms. The damage to the
Government from a delayed filing may not be confined only to the protested procurement
but may well also affect previous and contemporary procurements and the Government's
ability to keep projects on schedule via future procurements. A late filing may also
disrupt the Government's budgeting and fiscal expenditure process and could easily result
in funding for projects being reduced or canceled. Particularly in the rapidly-changing
area of computer and telecommunication technology, delay caused by a late filing may
prevent the Government from acquiring the latest technology without either reopening the
procurement or beginning the procurement anew.
Prejudice may extend beyond the Government.
See footnote 12 The contract awardee can be
prejudiced if it has commenced contract performance or has placed orders for long-lead
items. A late filing will also necessarily increase bid and proposal costs of the awardee,
and other offerors, impacting their indirect rate charges and, thus, their ability to compete
successfully in other acquisitions. Offerors can suffer further prejudice from a late filing
by having to maintain their proposal team in place, thereby preventing them from
working on other acquisitions. Further, a late filing may well place undue burdens on the
careers of employees expecting to perform the contract, either forcing them to accept a
period of unemployment or possibly abandon their commitment to the project and seek
work elsewhere. Naturally, any loss of proposed employees may severely disrupt an
offeror's ability to perform.
Finally, we note that no administrative protest forum has ever allowed more than
two weeks from the discovery of the basis of the protest, for a protest to be filed.
Therefore, we encourage the Court to establish a special rule that parallels the GAO's
timeliness regulations at 4 C.F.R. § 21.2. Issuing such rules would implement the clear
intent of Congress, and at the same time, establish a clear, bright line that would aid in
the uniform treatment of cases.
E. The Court Should Require The Posting of Security.
Pursuant to the Rules of the Court of Federal Claims (RCFC) 65(c), we expect that
agencies will seek, and the Court will require, security in cases where there are real costs
to the Government attendant on delay due to an injunction. The costs to agencies associated with delays attendant to injunctions are quite serious, even if difficult to
calculate. The Government, even in a preaward situation, must absorb the costs of delay
if the contract cannot be awarded or executed on schedule. Attention should be paid to
losses in efficiency, operating capacity, and the calculation of costs thereof by the agency,
and security should be based accordingly. Such costs are difficult, but not impossible to
approximate. If necessary, agencies should be willing to produce affidavits on these
issues.
In general, seeking an injunction from the Court should not be a cost free exercise.
This is particularly true where the plaintiff is the incumbent contractor and would
benefit, through extended contract performance, from delays resulting from the litigation.
The Government (and, accordingly, the taxpayer) pays a real price for every contract or
award that is enjoined.
In post award protests, contract awardees often incur costs that must be reimbursed
by the procuring agencies. A contractor may pass on to the Government storage costs for
equipment and supplies ordered, cancellation charges, or certain employee compensation.
Additionally, the incumbent contractor's costs often rise due to the uncertainty of its
employees and subcontractors, who cannot know how the suit will be resolved; in the
meantime, equipment leases may become more expensive (for example, equipment
originally leased for a year may convert to a month-to-month basis).
VI. The New Statute Limits The Available Monetary Relief.
Section 12(b)(2) of the Administrative Dispute Resolution Act of 1996, codified at
28 U.S.C. § 1491(b)(2), provides:
To afford relief in such action, the courts may award any
relief that the court considers proper, including declaratory and injunctive relief except that any monetary relief shall be
limited to bid preparation and proposal costs.
(Emphasis added.) We believe that Congress meant what it said. The only monetary
relief the Court may award in an action under Section 1491(b), is bid preparation and
proposal costs. Other forms of monetary relief, that might formerly have been considered
available cannot be awarded by the Court.
Suggested Issues "Not For Consideration"
1. Contract administration issues. Contract administration issues are more
properly subject to review under the CDA. That act provides for remedies and
review procedures which afford an exclusive means of addressing contract
administration issues.
2. Small Business Administration (SBA) issues. Size classifications of businesses
are within the sole discretion of the SBA.
3. Affirmative responsibility determinations. Challenges to determinations of a
would-be contractor's responsibility are matters necessarily subject to agency
discretion.
4. Protests filed in other jurisdictions. Out of comity, it would be beneficial to the
orderly conduct of litigation if the Court would defer to actions already filed in
other fora, such as the district courts. See, e.g., 28 U.S.C. § 1500. Similarly, the
Court should hesitate to take cognizance over a suit involving the same issues that
are being raised at the GAO.
5. Untimely protests. Protest issues that are not raised and addressed expeditiously
can unnecessarily disrupt the procurement process, and, thereby jeopardize the
fulfillment of critical government requirements. The Court should adopt
timeliness rules substantially similar to those used by the GAO. The GAO adopted
its timeliness rules based on the critical importance of beginning performance on a
new contract. Unlike the adjudication of claims, a stay or restraining order affects
the ability of the Government to obtain new goods or services and to perform
essential missions. Delays in contract performance can jeopardize the fielding of
critical weapons systems and considerably increase the cost of performance, as
contractors incur storage costs on equipment, maintain commitments to
subcontractors, and pay for idle employees.
6. Suits not brought by interested parties. Both the Court and the GAO
jurisdictional statutes limit the availability of protest relief to interested parties.
We suggest that the Court adopt the Federal Circuit's definition of an interested
party in determining who may bring an action under the Court's new jurisdiction.
The Federal Circuit has held recently that for a plaintiff to establish prejudice, and
thus to show that it is an interested party, it must demonstrate "a reasonable
likelihood, not just a reasonable possibility," that it would have received the
contract award but for the improper government action. Data Gen. Corp. v.
Johnson, 78 F.3d 1556, 1563 (Fed. Cir. 1996).
7. Subcontract protests. Protest recourse should be limited to parties with privity
(or potential privity) of contract with the Government, and not be available to
subcontractors or potential subcontractors.
8. Premature protests based on anticipated agency action. Matters that are not
yet ripe for litigation should not be subject to protest.
9. Academic protests. Protests regarding matters that are moot (i.e., no relief is
possible), should not be permitted.
10. Reprocurements. Because of the wide discretion given to contracting officers
allowing them to use any appropriate acquisition method in a reprocurement (FAR
49.402-6), and permitting them to conduct reprocurements obtaining competition
only "to the extent practicable," no meaningful standard of review applies to
reprocurements, and therefore they should not be subject to protest.
11. Actions that involve criminal allegations. Any procurement action that is
potentially subject to criminal investigation and prosecution by the Department of
Justice, to include violations of the Anti-kickback, Anti-trust, or Anti-dumping
statutes, should not be subject to protest.
12. Debarments. The GAO will look at procedural issues related to a debarment, but
will not look at the merits of the debarment decision. Substantive debarment
matters should not be adjudicated pursuant to the new statute.
13. Other agency actions under statutes providing broad grants of discretion
(e.g., attorney selections by the Attorney General under the Criminal Justice Act).
These are matters again for which there is no applicable standard of review, due to
the broad discretion exercised by agencies regarding these matters. See 5 U.S.C. §
701(a)(2).
14. Complaints lacking sufficient detail or failing to state a ground for relief.
Protests based on indeterminable issues should be dismissed either sua sponte or at
the motion of the Government. See, e.g., RCFC 12(b)(4), similar to Fed. R. Civ. P.
12(b)(6).
15. Agency overrides of GAO bid protest automatic stays. The GAO has
historically not reviewed the override decisions of an agency,
See footnote 13 based on the clear
legal authority of agencies to make such discretionary decisions. However, under
the Administrative Procedure Act, Federal district courts sometimes have reviewed
agency override decisions in the past. See, e.g., Dairy Maid Dairy v. United
States, 837 F. Supp. 1370 (E.D. Va. 1993). Nothing in the amended 1491(b)
indicates that this Court should exercise jurisdiction over agency stay decisions.
Because the statute permits a disappointed offeror to seek relief in this Court, the
need for a challenge to an agency override is not apparent.
Footnote: 1 The Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320.
Last Updated: April 22, 1997